Seattle Housing Map

Neighborhoods

New housing construction in Belltown, Seattle: every permit and application, units completed and under construction, mapped by site.

Weekly recap Back to map Stats/About

Neighborhoods / Downtown

Belltown

2020: 112 permitted, 166 applied, 0 completed2021: 459 permitted, 0 applied, 60 completed2022: 387 permitted, 222 applied, 0 completed2023: 324 permitted, 219 applied, 1 completed2024: 1 permitted, 84 applied, 1 completed2025: 0 permitted, 120 applied, 1,106 completed2026: 237 permitted, 277 applied, 0 completed
Under construction 237
Jan 2020: 60 under constructionFeb 2020: 172 under constructionMar 2020: 172 under constructionApr 2020: 172 under constructionMay 2020: 172 under constructionJun 2020: 172 under constructionJul 2020: 172 under constructionAug 2020: 172 under constructionSep 2020: 172 under constructionOct 2020: 172 under constructionNov 2020: 172 under constructionDec 2020: 172 under constructionJan 2021: 631 under constructionFeb 2021: 631 under constructionMar 2021: 571 under constructionApr 2021: 571 under constructionMay 2021: 571 under constructionJun 2021: 571 under constructionJul 2021: 571 under constructionAug 2021: 571 under constructionSep 2021: 571 under constructionOct 2021: 571 under constructionNov 2021: 571 under constructionDec 2021: 571 under constructionJan 2022: 783 under constructionFeb 2022: 783 under constructionMar 2022: 783 under constructionApr 2022: 783 under constructionMay 2022: 783 under constructionJun 2022: 783 under constructionJul 2022: 783 under constructionAug 2022: 783 under constructionSep 2022: 783 under constructionOct 2022: 783 under constructionNov 2022: 783 under constructionDec 2022: 783 under constructionJan 2023: 783 under constructionFeb 2023: 1,107 under constructionMar 2023: 1,107 under constructionApr 2023: 1,107 under constructionMay 2023: 1,106 under constructionJun 2023: 1,106 under constructionJul 2023: 1,106 under constructionAug 2023: 1,106 under constructionSep 2023: 1,106 under constructionOct 2023: 1,106 under constructionNov 2023: 1,106 under constructionDec 2023: 1,106 under constructionJan 2024: 1,106 under constructionFeb 2024: 1,106 under constructionMar 2024: 1,106 under constructionApr 2024: 1,107 under constructionMay 2024: 1,107 under constructionJun 2024: 1,107 under constructionJul 2024: 1,107 under constructionAug 2024: 1,107 under constructionSep 2024: 1,107 under constructionOct 2024: 1,107 under constructionNov 2024: 1,106 under constructionDec 2024: 1,106 under constructionJan 2025: 1,106 under constructionFeb 2025: 1,106 under constructionMar 2025: 1,106 under constructionApr 2025: 1,106 under constructionMay 2025: 894 under constructionJun 2025: 894 under constructionJul 2025: 459 under constructionAug 2025: 459 under constructionSep 2025: 459 under constructionOct 2025: 459 under constructionNov 2025: 0 under constructionDec 2025: 0 under constructionJan 2026: 0 under constructionFeb 2026: 0 under constructionMar 2026: 0 under constructionApr 2026: 0 under constructionMay 2026: 0 under constructionJun 2026: 0 under constructionJul 2026: 154 under constructionAug 2026: 154 under constructionSep 2026: 154 under constructionOct 2026: 237 under constructionNov 2026: 237 under construction
Housing projects in Belltown status

Projects in Belltown

Under construction 2 addresses, 237 units

2601 Elliott Ave
2601 Elliott Ave 154 apartments in Belltown, applied in February 2026, under construction since August 2026, 1/4 construction milestones passed, last milestone passed August 18, 2026.
2402 2nd Ave
2402 2nd Ave 83 apartments in Belltown, applied in September 2024, under construction since October 2026, 1/4 construction milestones passed, last milestone passed October 29, 2026.

Applied 15 addresses, 2,925 units

2033 4th Ave
2033 4th Ave 400 apartments in Belltown, applied in May 2019, last activity in April 2024.
210 Wall St
210 Wall St 275 apartments in Belltown, applied in April 2016, last activity in November 2019.
1903 5th Ave
1903 5th Ave 233 apartments in Belltown, applied in September 2017, last activity in May 2026.
110 Clay St
110 Clay St 221 apartments in Belltown, applied in June 2022, last activity in September 2025.
3000 Western Ave
3000 Western Ave 219 apartments in Belltown, applied in February 2023, corrections submitted in November 2026.
2616 Western Ave
2616 Western Ave 182 apartments in Belltown, applied in April 2019, last activity in June 2025.
2224 2nd Ave
2224 2nd Ave 175 apartments in Belltown, applied in January 2019, last activity in November 2025.
2407 1st Ave
2407 1st Ave 166 apartments in Belltown, applied in January 2020, last activity in May 2024.
2333 3rd Ave
2333 3rd Ave 165 apartments in Belltown, applied in September 2026.
307 Broad St
307 Broad St 152 apartments in Belltown, applied in September 2015, withdrawn in February 2025.
2205 1st Ave
2205 1st Ave 123 apartments in Belltown, applied in July 2026, last activity in August 2026.
3031 Western Ave
3031 Western Ave 120 apartments in Belltown, applied in December 2025, no activity since.
1915 3rd Ave
1915 3rd Ave 107 apartments in Belltown, applied in April 2016, last activity in May 2026.

Completed 18 addresses, 2,974 units

2116 4th Ave
2116 4th Ave 327 apartments in Belltown, 43 stories, applied in September 2008, completed in March 2019.
2208 4th Ave
2208 4th AveKaye 323 apartments in Belltown, 30 stories, applied in October 2018, completed in July 2025.
225 Cedar St
225 Cedar St 298 apartments in Belltown, 27 stories, applied in May 2011, completed in October 2014.
314 Bell St
314 Bell St 212 apartments in Belltown, applied in October 2018, completed in May 2025.
2105 5th Ave
2105 5th Ave 188 apartments in Belltown, 24 stories, applied in April 2006, completed in October 2013.
2720 4th Ave
2720 4th Ave 161 units in Belltown, applied in September 2011, completed in September 2014.
2134 Western Ave
2134 Western Ave 150 apartments in Belltown, 7 stories, applied in December 2014, completed in July 2018.
2521 Western Ave
2521 Western Ave 137 apartments in Belltown, 12 stories, applied in March 2013, completed in June 2015.
2334 Elliott Ave
2334 Elliott Ave 136 apartments in Belltown, 7 stories, applied in October 2011, completed in September 2014.
2401 3rd Ave
2401 3rd AveO2 132 apartments in Belltown, 12 stories, applied in December 2015, completed in June 2019.
62 Cedar St
62 Cedar St 132 apartments in Belltown, 13 stories, applied in April 2011, completed in October 2013.
303 Battery St
303 Battery St3ZERO3 112 apartments in Belltown, 15 stories, applied in February 2019, completed in July 2025.
101 Denny Way
101 Denny Way 83 apartments in Belltown, 6 stories, applied in May 2014, completed in February 2017.
2815 Elliott Ave
2815 Elliott Ave 62 apartments in Belltown, 6 stories, applied in September 2016, completed in July 2019.
3010 1st Ave
3010 1st Ave 60 apartments in Belltown, 6 stories, applied in January 2016, completed in March 2021.