New housing construction in Ballard, Seattle: every permit and application, units completed and under construction, mapped by site.

Weekly recap Back to map Stats/About

Neighborhoods

Ballard

2020: 337 permitted, 627 applied, 418 completed2021: 365 permitted, 671 applied, 491 completed2022: 348 permitted, 523 applied, 300 completed2023: 547 permitted, 85 applied, 466 completed2024: 434 permitted, 69 applied, 266 completed2025: 257 permitted, 148 applied, 470 completed2026: 319 permitted, 327 applied, 142 completed
Under construction 470
Jan 2020: 809 under constructionFeb 2020: 754 under constructionMar 2020: 677 under constructionApr 2020: 674 under constructionMay 2020: 832 under constructionJun 2020: 820 under constructionJul 2020: 729 under constructionAug 2020: 738 under constructionSep 2020: 744 under constructionOct 2020: 785 under constructionNov 2020: 758 under constructionDec 2020: 761 under constructionJan 2021: 779 under constructionFeb 2021: 771 under constructionMar 2021: 476 under constructionApr 2021: 562 under constructionMay 2021: 553 under constructionJun 2021: 552 under constructionJul 2021: 568 under constructionAug 2021: 523 under constructionSep 2021: 511 under constructionOct 2021: 506 under constructionNov 2021: 566 under constructionDec 2021: 579 under constructionJan 2022: 697 under constructionFeb 2022: 690 under constructionMar 2022: 726 under constructionApr 2022: 711 under constructionMay 2022: 696 under constructionJun 2022: 719 under constructionJul 2022: 554 under constructionAug 2022: 548 under constructionSep 2022: 548 under constructionOct 2022: 544 under constructionNov 2022: 631 under constructionDec 2022: 622 under constructionJan 2023: 529 under constructionFeb 2023: 767 under constructionMar 2023: 762 under constructionApr 2023: 750 under constructionMay 2023: 742 under constructionJun 2023: 741 under constructionJul 2023: 720 under constructionAug 2023: 720 under constructionSep 2023: 623 under constructionOct 2023: 624 under constructionNov 2023: 623 under constructionDec 2023: 617 under constructionJan 2024: 607 under constructionFeb 2024: 619 under constructionMar 2024: 598 under constructionApr 2024: 674 under constructionMay 2024: 682 under constructionJun 2024: 599 under constructionJul 2024: 601 under constructionAug 2024: 612 under constructionSep 2024: 624 under constructionOct 2024: 618 under constructionNov 2024: 624 under constructionDec 2024: 551 under constructionJan 2025: 666 under constructionFeb 2025: 437 under constructionMar 2025: 417 under constructionApr 2025: 420 under constructionMay 2025: 417 under constructionJun 2025: 407 under constructionJul 2025: 413 under constructionAug 2025: 405 under constructionSep 2025: 430 under constructionOct 2025: 343 under constructionNov 2025: 343 under constructionDec 2025: 328 under constructionJan 2026: 332 under constructionFeb 2026: 318 under constructionMar 2026: 314 under constructionApr 2026: 295 under constructionMay 2026: 522 under constructionJun 2026: 516 under constructionJul 2026: 501 under constructionAug 2026: 517 under constructionSep 2026: 508 under constructionOct 2026: 499 under constructionNov 2026: 470 under construction
Housing projects in Ballard status

Projects in Ballard

Under construction 20 addresses, 470 units

1740 NW Market St
1740 NW Market St 239 apartments in Ballard, applied in June 2018, under construction since June 2026, 1/4 construction milestones passed, last milestone passed June 9, 2026.
1761 NW 57th St
1761 NW 57th St 76 apartments in Ballard, applied in June 2019, under construction since January 2025, 3/4 construction milestones passed, last milestone passed July 17, 2026.
2002 NW 56th St
2002 NW 56th St 48 apartments in Ballard, applied in December 2019, under construction since January 2025, 3/4 construction milestones passed, last milestone passed August 6, 2026.
849 NW Market St
849 NW Market St 35 apartments in Ballard, applied in October 2019, under construction since February 2026, 2/4 construction milestones passed, last milestone passed June 4, 2026.
5621 22nd Ave NW
5621 22nd Ave NW 23 apartments in Ballard, applied in June 2025, under construction since October 2026, 1/4 construction milestones passed, last milestone passed October 21, 2026.
922 NW 54th St8 townhomes in Ballard, applied in April 2023, under construction since August 2024, 4/4 construction milestones passed, last milestone passed October 30, 2026. 840 NW Market St6 townhomes in Ballard, applied in November 2022, under construction since October 2023, 4/4 construction milestones passed, last milestone passed October 15, 2026. 2213 NW 62nd St6 townhomes in Ballard, applied in January 2025, under construction since July 2026, 2/4 construction milestones passed, last milestone passed October 16, 2026. 6216 17th Ave NW5 townhomes in Ballard, applied in April 2021, at final inspection. 1521 NW 63rd St4 duplex homes in Ballard, applied in July 2024, under construction since May 2025, 4/4 construction milestones passed, last milestone passed December 31, 2025. 3050 NW 64th St4 duplex homes in Ballard, applied in January 2026, under construction since August 2026, 2/4 construction milestones passed, last milestone passed October 22, 2026. 3021 NW 62nd St3 units (2 houses, 1 attached ADU) in Ballard, applied in August 2025, under construction since August 2026, 3/4 construction milestones passed, last milestone passed November 4, 2026. 903 NW 64th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, applied in April 2025, under construction since October 2025, 4/4 construction milestones passed, last milestone passed May 6, 2026. 6230 7th Ave NW3 units (1 detached ADU, 2 duplex homes) in Ballard, applied in June 2025, under construction since January 2026, 3/4 construction milestones passed, last milestone passed June 5, 2026. 5620 6th Ave NW2 units (1 house, 1 attached ADU) in Ballard, applied in November 2024, under construction since July 2025, 4/4 construction milestones passed, last milestone passed January 20, 2026. 6411 11th Ave NW1 detached ADU in Ballard, applied in April 2025, under construction since October 2026, 2/4 construction milestones passed, last milestone passed November 13, 2026. 1915 NW 65th St1 apartment in Ballard, applied in May 2023, at final inspection. 617 NW 48th St1 house in Ballard, applied in November 2025, under construction since October 2026, 1/4 construction milestones passed, last milestone passed October 6, 2026. 903 NW 61st St1 attached ADU in Ballard, applied in October 2025, under construction since April 2026, 4/4 construction milestones passed, last milestone passed September 4, 2026. 5843 3rd Ave NW1 unit in Ballard, applied in September 2023, under construction since May 2026, 1/4 construction milestones passed, last milestone passed July 29, 2026.

Applied 72 addresses, 1,920 units

6400 8th Ave NW
6400 8th Ave NW 300 apartments in Ballard, applied in July 2026, last activity in August 2026.
907 NW Market St
907 NW Market St 228 apartments in Ballard, applied in December 2019, corrections requested in August 2026.
5710 22nd Ave NW
5710 22nd Ave NW 206 apartments in Ballard, applied in July 2021, last activity in January 2026.
2401 NW Market St
2401 NW Market St 178 apartments in Ballard, applied in September 2022, corrections requested in January 2025.
904 NW Market St
904 NW Market St 171 apartments in Ballard, applied in October 2020, last activity in April 2026.
5011 15th Ave NW
5011 15th Ave NW 136 apartments in Ballard, applied in December 2017, last activity in December 2023.
1552 NW 52nd St
1552 NW 52nd St 122 apartments in Ballard, applied in January 2022, land use permit issued in May 2024.
2501 NW Market St
2501 NW Market St 110 apartments in Ballard, applied in December 2020, land use permit issued in December 2024.
2030 NW 57th St
2030 NW 57th St 60 apartments in Ballard, applied in March 2025, last activity in April 2025.
1544 NW 52nd St
1544 NW 52nd St 58 apartments in Ballard, applied in December 2018, last activity in March 2026.
6015 15th Ave NW
6015 15th Ave NW 49 apartments in Ballard, applied in May 2023, corrections requested in May 2026.
5409 Leary Ave NW
5409 Leary Ave NW 48 apartments in Ballard, applied in September 2018, last activity in November 2026.
1431 NW 65th St
1431 NW 65th St 43 apartments in Ballard, applied in June 2018, corrections submitted in November 2024.
929 NW 57th St
929 NW 57th St 26 apartments in Ballard, applied in September 2019, permit issued in January 2026.
3037 NW 56th St
3037 NW 56th St 19 apartments in Ballard, applied in May 2021, corrections requested in December 2024.
1138 NW 61st St
1138 NW 61st St 16 apartments in Ballard, applied in February 2022, last activity in March 2025.
1526 NW 53rd St
1526 NW 53rd St 11 townhomes in Ballard, applied in April 2025, last activity in May 2025.
1449 NW 65th St8 apartments in Ballard, applied in December 2016, withdrawn in October 2026. 844 NW Market St6 townhomes in Ballard, applied in December 2022, last activity in November 2026. 935 NW 56th St6 townhomes in Ballard, applied in February 2026, corrections requested in September 2026. 832 NW Market St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in October 2023, last activity in April 2026. 909 NW 56th St6 townhomes in Ballard, applied in July 2021, expired in October 2025. 828 NW Market St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in September 2021, corrections submitted in July 2025. 820 NW Market St6 townhomes in Ballard, applied in July 2021, last activity in April 2025. 5700 20th Ave NW5 townhomes in Ballard, applied in April 2025, last activity in August 2025. 815 NW 51st St4 units (2 houses, 2 duplex homes) in Ballard, applied in August 2026, last activity in November 2026. 931 A NW 59th St4 units (2 houses, 2 duplex homes) in Ballard, applied in June 2025, corrections requested in November 2026. 2432 NW 56th St4 apartments in Ballard, applied in June 2018, last activity in October 2026. 2436 NW 56th St4 duplex homes in Ballard, applied in June 2026, no activity since. 1118 NW 59th St4 duplex homes in Ballard, applied in March 2025, corrections requested in October 2025. 2207 NW 61st St4 duplex homes in Ballard, applied in July 2025, no activity since. 2638 NW 64th St4 units (1 house, 3 townhomes) in Ballard, applied in July 2019, expired in May 2025. 822 NW 51st St4 duplex homes in Ballard, applied in April 2021, expired in March 2025. 2630 NW 63rd St4 duplex homes in Ballard, applied in April 2023, last activity in February 2025. 1403 NW 59th St3 townhomes in Ballard, applied in October 2022, expired in July 2026. 1111 NW 65th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, applied in August 2022, last activity in June 2026. 1819 NW 65th St3 units (1 house, 2 duplex homes) in Ballard, applied in August 2025, corrections requested in May 2026. 1761 NW 61st St3 apartments in Ballard, applied in May 2020, expired in March 2025. 2049 NW 61st St2 houses in Ballard, applied in May 2018, last activity in October 2026. 6000 24th Ave NW2 apartments in Ballard, applied in June 2021, expired in September 2026. 2201 NW 62nd St2 duplex homes in Ballard, applied in September 2022, permit issued in February 2026. 5844 4th Ave NW2 duplex homes in Ballard, applied in July 2026, no activity since. 942 NW 58th St2 duplex homes in Ballard, applied in September 2025, corrections requested in May 2026. 5417 Ballard Ave NW2 apartments in Ballard, applied in June 2021, corrections requested in March 2026. 2412 NW 64th St2 duplex homes in Ballard, applied in April 2021, expired in December 2025. 1535 NW 63rd St2 houses in Ballard, applied in July 2018, withdrawn in June 2025. 6317 11th Ave NW2 houses in Ballard, applied in April 2025, no activity since. 1526 NW 59th St2 duplex homes in Ballard, applied in July 2015, expired in December 2018. 935 NW 60th St1 attached ADU in Ballard, applied in March 2025, last activity in November 2026. 2807 NW 63rd St1 detached ADU in Ballard, applied in November 2026. 950 NW 63rd St1 house in Ballard, applied in October 2026. 6246 7th Ave NW1 detached ADU in Ballard, applied in October 2026. 616 NW 47th St1 detached ADU in Ballard, applied in December 2025, permit issued in September 2026. 2407 NW 60th St1 apartment in Ballard, applied in December 2019, withdrawn in August 2026. 6049 6th Ave NW1 detached ADU in Ballard, applied in July 2026, no activity since. 3039 NW 64th St1 detached ADU in Ballard, applied in November 2022, expired in June 2026. 945 NW 62nd St1 house in Ballard, applied in May 2026, no activity since. 823 NW 65th St1 unit in Ballard, applied in April 2026, no activity since. 849 NW 60th St1 detached ADU in Ballard, applied in March 2026, last activity in April 2026. 2801 NW 60th St1 attached ADU in Ballard, applied in January 2023, last activity in April 2026. 6114 30th Ave NW1 detached ADU in Ballard, applied in April 2025, last activity in January 2026. 943 NW 58th St1 house in Ballard, applied in November 2025, no activity since. 2236 NW 60th St1 detached ADU in Ballard, applied in November 2025, no activity since. 6301 22nd Ave NW1 apartment in Ballard, applied in April 2023, last activity in September 2025. 6020 4th Ave NW1 attached ADU in Ballard, applied in July 2025, no activity since. 6015 20th Ave NW1 apartment in Ballard, applied in November 2024, withdrawn in February 2025. 2423 NW 64th St1 house in Ballard, applied in November 2024, last activity in December 2024. 1111 NW 56th St1 apartment in Ballard, applied in January 2024, corrections requested in December 2024. 1531 NW 60th St1 house in Ballard, applied in November 2017, withdrawn in December 2024. 4733 Shilshole Ave NW1 house in Ballard, applied in March 2019, land use permit issued in April 2024. 6016 4th Ave NWAn unstated number of homes in Ballard, applied in March 2025, expired in November 2026. 5300 34th Ave NWAn unstated number of homes in Ballard, applied in July 2026, no activity since.

Completed 438 addresses, 4,985 units

2428 NW Market St
2428 NW Market St 304 apartments in Ballard, 7 stories, applied in August 2011, completed in December 2014.
5343 Tallman Ave NW
5343 Tallman Ave NW 303 apartments in Ballard, applied in April 2012, completed in October 2015.
1500 NW Market St
1500 NW Market St 290 apartments in Ballard, 8 stories, applied in August 2007, completed in March 2021.
1400 NW Market St
1400 NW Market St 266 apartments in Ballard, 6 stories, applied in December 2008, completed in April 2013.
2318 NW Market St
2318 NW Market St 238 apartments in Ballard, applied in October 2021, completed in February 2025.
1701 NW 56th St
1701 NW 56th St 176 apartments in Ballard, 7 stories, applied in February 2015, completed in October 2018.
2417 NW Market St
2417 NW Market St 171 apartments in Ballard, 6 stories, applied in January 2018, completed in July 2022.
1702 NW 56th St
1702 NW 56th St 164 apartments in Ballard, 6 stories, applied in November 2015, completed in July 2019.
1760 NW 56th St
1760 NW 56th St 117 apartments in Ballard, 6 stories, applied in January 2012, completed in February 2016.
5711 24th Ave NW
5711 24th Ave NW 111 apartments in Ballard, 6 stories, applied in September 2010, completed in September 2015.
1537 NW 56th St
1537 NW 56th St 106 apartments in Ballard, 7 stories, applied in April 2011, completed in May 2017.
5601 24th Ave NW
5601 24th Ave NW 93 apartments in Ballard, 7 stories, applied in January 2014, completed in August 2016.
943 NW Market St
943 NW Market St 92 apartments in Ballard, 5 stories, applied in July 2020, completed in November 2023.
1100 NW 54th St
1100 NW 54th St 86 apartments in Ballard, 7 stories, applied in November 2018, completed in September 2023.
2035 NW 58th St
2035 NW 58th St 84 apartments in Ballard, 8 stories, applied in September 2022, completed in October 2025.
5601 22nd Ave NW
5601 22nd Ave NW 84 apartments in Ballard, 6 stories, applied in March 2014, completed in December 2016.
6400 15th Ave NW
6400 15th Ave NW 81 apartments in Ballard, 5 stories, applied in January 2019, completed in January 2023.
1710 NW 57th St
1710 NW 57th StLiam 80 apartments in Ballard, 5 stories, applied in March 2017, completed in February 2020.
6404 24th Ave NW
6404 24th Ave NW 75 apartments in Ballard, 5 stories, applied in November 2012, completed in May 2016.
5611 17th Ave NW
5611 17th Ave NWRiano 74 apartments in Ballard, 6 stories, applied in November 2015, completed in March 2020.
6301 15th Ave NW
6301 15th Ave NW 63 apartments in Ballard, 4 stories, applied in January 2015, completed in August 2019.
1514 NW 52nd St
1514 NW 52nd St 62 apartments in Ballard, 6 stories, applied in June 2016, completed in April 2019.
1501 NW 59th St
1501 NW 59th St 52 apartments in Ballard, 4 stories, applied in November 2017, completed in August 2021.
2014 NW 57th St
2014 NW 57th St 51 apartments in Ballard, 6 stories, applied in June 2012, completed in January 2015.
1731 NW 57th St
1731 NW 57th St 48 apartments in Ballard, 6 stories, applied in September 2014, completed in July 2017.
1506 NW 61st St
1506 NW 61st St 33 apartments in Ballard, 4 stories, applied in February 2015, completed in September 2017.
1443 NW 63rd St
1443 NW 63rd St 30 apartments in Ballard, 4 stories, applied in April 2016, completed in July 2019.
968 NW 54th St
968 NW 54th St 24 townhomes in Ballard, applied in January 2020, completed in November 2026.
1439 NW 60th St
1439 NW 60th St 22 apartments in Ballard, 4 stories, applied in September 2018, completed in March 2025.
2226 NW 58th St
2226 NW 58th St 20 apartments in Ballard, 6 stories, applied in November 2015, completed in November 2020.
901 NW 57th St
901 NW 57th St 14 townhomes in Ballard, applied in May 2020, completed in March 2024.
912 NW 56th St
912 NW 56th St 12 units (2 duplex homes, 7 townhomes, 3 apartments) in Ballard, applied in September 2019, completed in February 2023.
5300 9th Ave NW
5300 9th Ave NW 10 townhomes in Ballard, applied in July 2019, completed in November 2023.
2012 C NW 60th St
2012 C NW 60th St 10 units (2 houses, 2 duplex homes, 6 townhomes) in Ballard, applied in February 2018, completed in September 2021.
903 NW 56th St9 townhomes in Ballard, applied in July 2019, completed in August 2025. 851 NW 54th St9 townhomes in Ballard, applied in February 2020, completed in August 2023. 2203 NW 63rd St9 townhomes in Ballard, applied in January 2017, completed in July 2019. 2043 NW 60th St8 townhomes in Ballard, applied in June 2020, completed in July 2023. 902 NW 56th St8 units (2 duplex homes, 6 townhomes) in Ballard, applied in September 2020, completed in March 2023. 847 NW 57th St8 units (2 duplex homes, 6 townhomes) in Ballard, applied in August 2020, completed in January 2023. 920 NW 54th St8 townhomes in Ballard, applied in July 2019, completed in September 2021. 1438 NW 60th St8 apartments in Ballard, 4 stories, applied in June 2017, completed in November 2020. 6251 8th Ave NW8 townhomes in Ballard, applied in September 2017, completed in May 2020. 2632 NW 58th St8 units (4 duplex homes, 4 townhomes) in Ballard, applied in March 2017, completed in March 2019. 6000 26th Ave NW7 townhomes in Ballard, applied in January 2021, completed in September 2026. 1723 NW 63rd St7 townhomes in Ballard, applied in November 2023, completed in October 2025. 917 NW 51st St7 units (1 attached ADU, 6 townhomes) in Ballard, applied in February 2018, completed in September 2025. 5116 9th Ave NW7 townhomes in Ballard, applied in August 2021, completed in December 2024. 2622 NW 62nd St7 units (4 duplex homes, 3 townhomes) in Ballard, applied in November 2020, completed in September 2023. 916 NW 56th St7 townhomes in Ballard, applied in August 2020, completed in July 2023. 5615 26th Ave NW7 townhomes in Ballard, applied in September 2018, completed in May 2023. 832 NW 54th St7 townhomes in Ballard, applied in September 2020, completed in August 2022. 801 NW 50th St7 townhomes in Ballard, applied in July 2018, completed in January 2020. 2637 NW 59th St7 townhomes in Ballard, applied in July 2018, completed in November 2021. 6300 26th Ave NW7 townhomes in Ballard, applied in May 2018, completed in September 2020. 1121 NW 56th St7 townhomes in Ballard, applied in November 2017, completed in August 2019. 1117 NW 56th St7 townhomes in Ballard, applied in December 2017, completed in July 2019. 1703 NW 64th St7 townhomes in Ballard, applied in October 2015, completed in December 2017. 2230 NW 60th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in March 2022, completed in July 2026. 1136 NW 57th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in March 2023, completed in May 2026. 2208 NW 64th St6 duplex homes in Ballard, applied in March 2021, completed in October 2024. 2627 NW 59th St6 townhomes in Ballard, applied in January 2020, completed in December 2023. 2245 A NW 60th St6 units (3 houses, 3 attached ADUs) in Ballard, applied in August 2021, completed in June 2025. 923 NW 56th St6 townhomes in Ballard, applied in May 2021, completed in May 2025. 928 NW 56th St6 townhomes in Ballard, applied in November 2020, completed in November 2022. 1149 NW 56th St6 duplex homes in Ballard, applied in October 2022, completed in January 2025. 922 NW 56th St6 townhomes in Ballard, applied in August 2020, completed in April 2023. 828 NW 52nd St6 townhomes in Ballard, applied in October 2021, completed in June 2024. 824 NW 52nd St6 townhomes in Ballard, applied in September 2021, completed in June 2024. 1137 NW 59th St6 units (3 houses, 3 attached ADUs) in Ballard, 3 stories, applied in April 2022, completed in March 2024. 1127 NW 57th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in September 2019, completed in May 2021. 901 NW 58th St6 townhomes in Ballard, applied in January 2021, completed in July 2023. 2439 NW 61st St6 townhomes in Ballard, applied in April 2019, completed in October 2021. 6405 22nd Ave NW6 townhomes in Ballard, applied in August 2018, completed in April 2023. 5612 14th Ave NW6 townhomes in Ballard, applied in May 2019, completed in January 2023. 1124 NW 57th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in December 2019, completed in December 2022. 937 NW 56th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in November 2019, completed in December 2022. 921 NW 56th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in March 2020, completed in May 2022. 823 NW 54th St6 units (2 duplex homes, 4 townhomes) in Ballard, applied in April 2019, completed in April 2022. 2219 NW 62nd St6 townhomes in Ballard, applied in May 2019, completed in March 2022. 1151 NW 59th St6 units (3 houses, 3 attached ADUs) in Ballard, 3 stories, applied in August 2020, completed in February 2022. 6415 14th Ave NW6 townhomes in Ballard, applied in July 2018, completed in November 2021. 1133 NW 57th St6 townhomes in Ballard, applied in July 2019, completed in May 2021. 2437 NW 60th St6 townhomes in Ballard, applied in March 2019, completed in April 2021. 2630 NW 62nd St6 townhomes in Ballard, applied in June 2018, completed in March 2021. 6406 14th Ave NW6 townhomes in Ballard, applied in January 2018, completed in March 2021. 5806 17th Ave NW6 townhomes in Ballard, applied in January 2019, completed in November 2020. 2210 NW 59th St6 townhomes in Ballard, applied in March 2018, completed in November 2020. 6115 17th Ave NW6 townhomes in Ballard, applied in May 2018, completed in June 2020. 1153 NW 58th St5 townhomes in Ballard, applied in September 2022, completed in February 2026. 2412 NW 60th St5 units (2 duplex homes, 3 townhomes) in Ballard, applied in June 2023, completed in February 2026. 2419 NW 60th St5 units (2 duplex homes, 3 townhomes) in Ballard, applied in March 2022, completed in May 2024. 1534 NW 59th St5 townhomes in Ballard, applied in April 2022, completed in April 2024. 5400 9th Ave NW5 units (2 duplex homes, 3 townhomes) in Ballard, applied in June 2020, completed in January 2024. 839 NW 54th St5 units (1 house, 4 townhomes) in Ballard, applied in July 2020, completed in July 2023. 2638 NW 56th St5 units (4 duplex homes, 1 townhome) in Ballard, applied in May 2021, completed in February 2023. 2031 NW 63rd St5 units (1 house, 4 townhomes) in Ballard, applied in July 2018, completed in May 2021. 2023 NW 63rd St5 units (2 duplex homes, 3 townhomes) in Ballard, applied in June 2018, completed in June 2020. 929 NW 56th St5 units (2 houses, 1 attached ADU, 2 duplex homes) in Ballard, applied in September 2018, completed in May 2022. 2603 NW 63rd St5 townhomes in Ballard, applied in January 2016, completed in May 2022. 814 NW 54th St5 units (1 house, 4 townhomes) in Ballard, applied in December 2019, completed in April 2022. 1142 NW 57th St5 units (2 duplex homes, 3 townhomes) in Ballard, applied in April 2019, completed in March 2021. 1552 NW 58th St5 townhomes in Ballard, applied in September 2018, completed in June 2020. 2644 NW 59th St5 units (2 duplex homes, 3 townhomes) in Ballard, applied in March 2018, completed in May 2020. 6320 26th Ave NW5 units (2 duplex homes, 3 townhomes) in Ballard, applied in October 2016, completed in April 2020. 1552 NW 63rd St5 townhomes in Ballard, applied in November 2017, completed in October 2019. 702 NW 62nd St5 townhomes in Ballard, applied in August 2017, completed in October 2019. 1554 NW 60th St5 townhomes in Ballard, applied in February 2017, completed in November 2018. 1552 NW 62nd St5 townhomes in Ballard, applied in September 2014, completed in August 2017. 905 NW 60th St4 units (3 houses, 1 detached ADU) in Ballard, applied in November 2023, completed in November 2026. 2017 NW 64th St4 duplex homes in Ballard, applied in July 2025, completed in October 2026. 2608 NW 62nd St4 units (2 houses, 2 duplex homes) in Ballard, 3 stories, applied in December 2024, completed in August 2026. 1131 NW 60th St4 duplex homes in Ballard, applied in September 2024, completed in July 2026. 1759 NW 62nd St4 duplex homes in Ballard, applied in July 2024, completed in July 2026. 1143 NW 57th St4 duplex homes in Ballard, applied in June 2024, completed in June 2026. 1762 NW 60th St4 duplex homes in Ballard, applied in October 2024, completed in June 2026. 1127 NW 58th St4 duplex homes in Ballard, applied in March 2024, completed in May 2026. 2647 NW 63rd St4 duplex homes in Ballard, applied in December 2023, completed in April 2026. 928 NW 57th St4 duplex homes in Ballard, applied in February 2024, completed in April 2026. 813 NW 63rd St4 duplex homes in Ballard, applied in February 2022, completed in April 2026. 836 NW 50th St4 duplex homes in Ballard, applied in August 2024, completed in February 2026. 926 NW 58th St4 duplex homes in Ballard, applied in August 2024, completed in December 2025. 3014 NW 56th St4 duplex homes in Ballard, applied in June 2023, completed in December 2025. 2419 NW 57th St4 duplex homes in Ballard, applied in April 2016, completed in June 2025. 1516 NW 63rd St4 duplex homes in Ballard, applied in April 2022, completed in October 2025. 2035 NW 61st St4 townhomes in Ballard, applied in May 2024, completed in September 2025. 6057 7th Ave NW4 houses in Ballard, applied in September 2021, completed in April 2023. 1746 NW 62nd St4 duplex homes in Ballard, applied in July 2023, completed in August 2025. 1742 NW 62nd St4 duplex homes in Ballard, applied in July 2023, completed in August 2025. 836 NW 58th St4 units (2 houses, 2 attached ADUs) in Ballard, 3 stories, applied in August 2021, completed in May 2025. 2014 NW 62nd St4 duplex homes in Ballard, applied in October 2023, completed in April 2025. 1526 NW 62nd St4 duplex homes in Ballard, applied in October 2018, completed in February 2025. 1738 C NW 60th St4 units (2 houses, 2 attached ADUs) in Ballard, applied in March 2022, completed in January 2025. 922 NW 57th St4 duplex homes in Ballard, applied in January 2023, completed in October 2024. 1129 NW 60th St4 duplex homes in Ballard, applied in January 2021, completed in September 2024. 1127 NW 61st St4 units (2 houses, 2 attached ADUs) in Ballard, 3 stories, applied in March 2022, completed in July 2024. 925 NW 59th St4 houses in Ballard, applied in April 2022, completed in July 2024. 1119 NW 59th Ave4 duplex homes in Ballard, applied in March 2022, completed in June 2024. 1111 NW 59th St4 duplex homes in Ballard, applied in March 2022, completed in June 2024. 2039 NW 62nd St4 duplex homes in Ballard, applied in November 2021, completed in June 2024. 2611 NW 60th St4 duplex homes in Ballard, applied in June 2021, completed in March 2024. 2212 NW 60th St4 townhomes in Ballard, applied in May 2016, completed in January 2024. 939 NW 52nd St4 duplex homes in Ballard, applied in May 2019, completed in February 2022. 5514 11th Ave NW4 townhomes in Ballard, applied in September 2019, completed in October 2021. 2427 NW 64th St4 duplex homes in Ballard, applied in April 2021, completed in July 2023. 820 NW 54th St4 duplex homes in Ballard, applied in May 2019, completed in January 2021. 6210 20th Ave NW4 units (1 house, 3 townhomes) in Ballard, applied in October 2020, completed in June 2023. 2227 NW 63rd St4 units (1 house, 1 attached ADU, 2 duplex homes) in Ballard, 3 stories, applied in September 2020, completed in May 2023. 701 NW 62nd St4 duplex homes in Ballard, applied in July 2021, completed in April 2023. 915 NW 52nd St4 units (1 house, 3 townhomes) in Ballard, applied in September 2018, completed in December 2020. 2006 NW 62nd St4 units (1 house, 2 duplex homes, 1 townhome) in Ballard, applied in July 2022, completed in March 2023. 819 NW 54th St4 duplex homes in Ballard, applied in November 2020, completed in March 2023. 1727 NW 64th St4 units (1 house, 3 townhomes) in Ballard, applied in January 2021, completed in March 2023. 1723 NW 64th St4 duplex homes in Ballard, applied in November 2020, completed in October 2022. 1509 NW 64th St4 duplex homes in Ballard, applied in August 2020, completed in August 2022. 1734 NW 62nd St4 duplex homes in Ballard, applied in November 2019, completed in July 2022. 1546 NW 64th St4 duplex homes in Ballard, applied in May 2020, completed in April 2022. 1142 NW 59th St4 duplex homes in Ballard, applied in July 2020, completed in March 2022. 901 NW 51st St4 townhomes in Ballard, applied in March 2018, completed in March 2022. 823 NW 51st St4 duplex homes in Ballard, applied in March 2020, completed in February 2022. 2010 NW 63rd St4 duplex homes in Ballard, applied in February 2020, completed in June 2021. 2211 NW 63rd St4 units (1 house, 3 townhomes) in Ballard, applied in April 2018, completed in May 2021. 1520 NW 61st St4 units (1 house, 3 townhomes) in Ballard, applied in October 2018, completed in March 2021. 2233 NW 62nd St4 units (1 house, 3 townhomes) in Ballard, applied in July 2018, completed in February 2021. 2023 NW 62nd St4 units (1 house, 3 townhomes) in Ballard, applied in March 2018, completed in January 2021. 1750 NW 60th St4 units (1 duplex home, 3 townhomes) in Ballard, applied in May 2018, completed in December 2020. 5507 4th Ave NW4 townhomes in Ballard, applied in May 2017, completed in August 2020. 807 NW 51st St4 units (1 house, 3 townhomes) in Ballard, applied in March 2018, completed in May 2020. 2226 NW 63rd St4 units (1 house, 3 townhomes) in Ballard, applied in December 2017, completed in March 2020. 2045 NW 63rd St4 townhomes in Ballard, applied in May 2018, completed in February 2020. 807 NW 52nd St4 units (1 house, 3 townhomes) in Ballard, applied in April 2017, completed in January 2020. 2220 NW 64th St4 units (1 house, 3 townhomes) in Ballard, applied in July 2017, completed in January 2020. 1737 NW 61st St4 units (1 house, 3 townhomes) in Ballard, applied in November 2017, completed in January 2020. 1537 NW 59th St4 units (1 house, 3 townhomes) in Ballard, applied in August 2016, completed in January 2020. 2018 NW 62nd St4 units (1 house, 3 townhomes) in Ballard, applied in May 2017, completed in October 2019. 2444 NW 64th St4 units (1 house, 3 townhomes) in Ballard, applied in September 2017, completed in August 2019. 2251 NW 59th St4 apartments in Ballard, 3 stories, applied in February 2018, completed in August 2019. 2414 NW 64th St4 units (1 house, 3 townhomes) in Ballard, applied in October 2017, completed in August 2019. 6207 7th Ave NW4 units (1 house, 3 townhomes) in Ballard, applied in April 2017, completed in July 2019. 2224 NW 62nd St4 units (1 house, 3 townhomes) in Ballard, applied in August 2017, completed in May 2019. 2629 NW 63rd St4 townhomes in Ballard, applied in July 2015, completed in July 2017. 2048 NW 61st St4 units (1 house, 3 townhomes) in Ballard, applied in August 2017, completed in May 2019. 1532 NW 60th St4 units (1 house, 3 townhomes) in Ballard, applied in January 2017, completed in April 2019. 2223 NW 63rd St4 units (1 house, 3 townhomes) in Ballard, applied in August 2017, completed in March 2019. 824 NW 63rd St4 units (1 house, 3 townhomes) in Ballard, applied in September 2017, completed in February 2019. 2428 NW 63rd St4 units (1 house, 3 townhomes) in Ballard, applied in December 2016, completed in January 2019. 1408 NW 57th St4 apartments in Ballard, 3 stories, applied in September 2016, completed in May 2018. 2426 NW 62nd St4 units (1 house, 3 townhomes) in Ballard, applied in June 2016, completed in February 2018. 928 NW 51st St4 units (1 house, 3 townhomes) in Ballard, applied in August 2016, completed in October 2017. 6021 22nd Ave NW4 townhomes in Ballard, applied in November 2015, completed in August 2017. 3029 NW 56th St4 townhomes in Ballard, applied in February 2016, completed in July 2017. 2431 NW 62nd St4 units (1 house, 3 townhomes) in Ballard, applied in March 2016, completed in May 2017. 307 NW 52nd St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, applied in January 2025, completed in October 2026. 1510 NW 59th St3 units (1 house, 2 duplex homes) in Ballard, applied in December 2024, completed in August 2026. 6226 7th Ave NW3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in March 2022, completed in August 2026. 6317 26th Ave NW3 townhomes in Ballard, applied in November 2016, completed in August 2026. 841 NW 61st St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in July 2023, completed in May 2026. 949 NW 61st St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in October 2024, completed in December 2025. 943 NW 56th St3 townhomes in Ballard, applied in September 2019, completed in December 2025. 1120 NW 61st St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in February 2024, completed in December 2025. 2842 NW 62nd St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 1 story, applied in September 2023, completed in October 2025. 335 NW 47th St3 units (1 house, 2 attached ADUs) in Ballard, 3 stories, applied in January 2023, completed in June 2025. 639 NW 54th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in September 2022, completed in June 2025. 322 NW 47th St3 units (1 house, 2 attached ADUs) in Ballard, 3 stories, applied in December 2023, completed in June 2025. 1801 C NW 65th St3 houses in Ballard, applied in December 2021, completed in May 2025. 333 NW 47th St3 units (houses and attached ADUs) in Ballard, 3 stories, applied in January 2023, completed in April 2025. 6234 5th Ave NW3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in August 2023, completed in March 2025. 2826 NW 63rd St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in March 2023, completed in January 2025. 716 NW 60th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in May 2022, completed in December 2024. 2239 NW 62nd St3 houses in Ballard, applied in February 2018, completed in July 2024. 826 NW 56th St3 units (1 house, 2 duplex homes) in Ballard, applied in May 2019, completed in June 2024. 1143 NW 59th St3 townhomes in Ballard, applied in March 2022, completed in April 2024. 2825 NW 57th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in April 2022, completed in April 2024. 837 NW 53rd St3 units (1 house, 2 duplex homes) in Ballard, applied in April 2022, completed in January 2024. 1117 NW 57th St3 townhomes in Ballard, applied in November 2019, completed in December 2021. 833 NW 53rd St3 units (1 house, 2 duplex homes) in Ballard, applied in April 2022, completed in January 2024. 1119 NW 57th St3 townhomes in Ballard, applied in July 2019, completed in December 2021. 846 NW 51st St3 townhomes in Ballard, applied in November 2018, completed in April 2021. 2626 NW 62nd St3 houses in Ballard, applied in March 2016, completed in September 2023. 2638 NW 63rd St3 houses in Ballard, applied in February 2022, completed in September 2023. 1751 NW 61st St3 houses in Ballard, applied in October 2016, completed in September 2023. 647 NW 54th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in April 2021, completed in May 2023. 2436 A NW 64th St3 houses in Ballard, applied in March 2019, completed in September 2020. 602 NW 48th St3 units (1 house, 2 attached ADUs) in Ballard, 3 stories, applied in March 2021, completed in April 2023. 5513 6th Ave NW3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in June 2021, completed in March 2023. 2419 NW 63rd St3 houses in Ballard, applied in January 2021, completed in February 2023. 901 NW 59th St3 townhomes in Ballard, applied in April 2021, completed in January 2023. 359 NW 47th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in May 2021, completed in December 2022. 2449 NW 61st St3 townhomes in Ballard, applied in February 2018, completed in March 2020. 2853 NW 63rd St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 2 stories, applied in October 2020, completed in November 2022. 3043 NW 65th St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in December 2020, completed in October 2022. 5507 5th Ave NW3 units (1 house, 2 duplex homes) in Ballard, applied in September 2020, completed in June 2022. 2206 NW 60th St3 townhomes in Ballard, applied in May 2016, completed in May 2022. 927 NW 62nd St3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in January 2020, completed in April 2022. 6212 7th Ave NW3 units (1 house, 1 attached ADU, 1 detached ADU) in Ballard, 3 stories, applied in September 2020, completed in February 2022. 818 NW 53rd St3 townhomes in Ballard, applied in June 2017, completed in July 2019. 933 NW 52nd St3 townhomes in Ballard, applied in May 2019, completed in November 2021. 1706 NW 63rd St3 townhomes in Ballard, applied in March 2017, completed in October 2021. 2422 NW 60th St3 townhomes in Ballard, applied in March 2018, completed in February 2021. 1528 NW 61st St3 townhomes in Ballard, applied in May 2018, completed in February 2021. 928 NW Leary Way3 apartments in Ballard, 3 stories, applied in December 2016, completed in July 2020. 806 NW 50th St3 townhomes in Ballard, applied in December 2017, completed in June 2020. 2009 NW 60th St3 houses in Ballard, applied in October 2016, completed in April 2020. 1707 NW 64th St3 houses in Ballard, applied in February 2018, completed in April 2020. 1733 NW 61st St3 apartments in Ballard, 3 stories, applied in September 2017, completed in February 2020. 2442 NW 60th St3 townhomes in Ballard, applied in March 2018, completed in January 2020. 2615 NW 60th St3 townhomes in Ballard, applied in January 2018, completed in January 2020. 1531 NW 65th St3 houses in Ballard, applied in August 2017, completed in January 2020. 2442 NW 61st St3 houses in Ballard, applied in November 2017, completed in December 2019. 2228 NW 63rd St3 townhomes in Ballard, applied in October 2017, completed in November 2019. 2656 NW 62nd St3 townhomes in Ballard, applied in March 2018, completed in July 2019. 2021 NW 60th St3 houses in Ballard, applied in December 2016, completed in July 2019. 814 NW 53rd St3 houses in Ballard, applied in December 2017, completed in May 2019. 3020 NW 56th St3 houses in Ballard, applied in October 2017, completed in May 2019. 2636 NW 58th St3 townhomes in Ballard, applied in November 2016, completed in March 2019. 1547 NW 59th St3 houses in Ballard, applied in August 2017, completed in January 2019. 1735 NW 62nd St3 houses in Ballard, applied in February 2017, completed in November 2018. 1711 NW 65th St3 houses in Ballard, applied in July 2017, completed in November 2018. 2011 NW 64th St3 townhomes in Ballard, applied in March 2017, completed in September 2018. 2430 NW 60th St3 townhomes in Ballard, applied in November 2016, completed in August 2018. 2225 NW 62nd St3 houses in Ballard, applied in May 2017, completed in June 2018. 2050 NW 62nd St3 houses in Ballard, applied in May 2017, completed in May 2018. 2515 NW 65th St3 townhomes in Ballard, applied in October 2015, completed in March 2018. 2035 A NW 62nd St3 houses in Ballard, applied in November 2016, completed in March 2018. 2216 NW 64th St3 townhomes in Ballard, applied in September 2016, completed in December 2017. 1746 NW 60th St3 houses in Ballard, applied in September 2016, completed in December 2017. 1743 C NW 63rd St3 townhomes in Ballard, applied in December 2016, completed in November 2017. 1744 NW 64th St3 units (1 house, 2 duplex homes) in Ballard, applied in January 2016, completed in November 2017. 1726 NW 60th St3 townhomes in Ballard, applied in July 2016, completed in October 2017. 2443 NW 62nd St3 houses in Ballard, applied in July 2016, completed in September 2017. 6105 A 22nd Ave NW3 houses in Ballard, applied in March 2016, completed in August 2017. 1415 NW 65th St3 units (1 house, 2 duplex homes) in Ballard, applied in January 2016, completed in August 2017. 2230 NW 62nd St3 houses in Ballard, applied in December 2015, completed in June 2017. 810 NW 63rd St3 townhomes in Ballard, applied in January 2016, completed in June 2017. 1811 NW 65th St3 units (1 house, 2 duplex homes) in Ballard, applied in April 2016, completed in May 2017. 1726 NW 64th St3 houses in Ballard, applied in January 2016, completed in May 2017. 6219 14th Ave NW3 townhomes in Ballard, applied in December 2015, completed in March 2017. 2039 NW 65th St3 houses in Ballard, applied in November 2015, completed in March 2017. 2218 A NW 61st St3 houses in Ballard, applied in March 2016, completed in February 2017. 1805 NW 65th St3 houses in Ballard, applied in October 2015, completed in December 2016. 5804 26th Ave NW3 apartments in Ballard, 1.5 stories, applied in August 2015, completed in November 2016. 2220 NW 62nd St2 duplex homes in Ballard, applied in June 2022, completed in June 2026. 2218 NW 62nd St2 duplex homes in Ballard, applied in January 2022, completed in June 2026. 6315 9th Ave NW2 units (1 house, 1 detached ADU) in Ballard, 2 stories, applied in July 2024, completed in April 2026. 1118 NW 63rd St2 units (1 house, 1 attached ADU) in Ballard, 2 stories, applied in March 2025, completed in April 2026. 809 NW 63rd St2 duplex homes in Ballard, applied in July 2022, completed in April 2026. 807 NW 63rd St2 duplex homes in Ballard, applied in March 2022, completed in April 2026. 5828 5th Ave NW2 units (1 house, 1 attached ADU) in Ballard, 2 stories, applied in February 2024, completed in March 2026. 1766 NW 61st St2 duplex homes in Ballard, 3 stories, applied in December 2014, completed in March 2026. 1522 NW 63rd St2 duplex homes in Ballard, applied in March 2020, completed in May 2023. 2037 NW 62nd St2 duplex homes in Ballard, applied in November 2021, completed in July 2024. 1133 NW 61st St2 units (1 house, 1 attached ADU) in Ballard, 2 stories, applied in August 2020, completed in September 2023. 1524 NW 63rd St2 houses in Ballard, applied in March 2021, completed in May 2023. 1518 NW 63rd St2 houses in Ballard, applied in January 2021, completed in May 2023. 2009 A NW 64th St2 houses in Ballard, applied in December 2016, completed in April 2023. 929 NW 52nd St2 duplex homes in Ballard, applied in September 2018, completed in October 2021. 857 NW 65th St2 units (1 attached ADU, 1 detached ADU) in Ballard, applied in November 2020, completed in June 2022. 1537 NW 60th St2 duplex homes in Ballard, applied in August 2016, completed in January 2022. 936 NW 58th St2 duplex homes in Ballard, applied in March 2020, completed in December 2021. 934 NW 58th St2 duplex homes in Ballard, applied in March 2020, completed in December 2021. 1144 NW 59th St2 houses in Ballard, applied in October 2019, completed in December 2021. 640 NW 47th St2 units (1 house, 1 attached ADU) in Ballard, 2 stories, applied in November 2019, completed in March 2021. 3042 NW 64th St2 units (1 house, 1 detached ADU) in Ballard, 3 stories, applied in September 2019, completed in January 2021. 833 NW 61st St2 units (1 house, 1 detached ADU) in Ballard, 2 stories, applied in August 2018, completed in July 2020. 1547 NW 60th St2 duplex homes in Ballard, applied in October 2017, completed in November 2019. 625 NW 48th St2 units (1 house, 1 detached ADU) in Ballard, 2 stories, applied in August 2016, completed in July 2019. 841 NW 62nd St2 houses in Ballard, applied in May 2017, completed in April 2019. 5221 Ballard Ave NW2 apartments in Ballard, 3 stories, applied in August 2015, completed in March 2019. 5839 4th Ave NW2 units (1 house, 1 attached ADU) in Ballard, 2 stories, applied in October 2017, completed in February 2019. 2016 NW 64th St2 duplex homes in Ballard, applied in December 2016, completed in November 2018. 1733 NW 63rd St2 duplex homes in Ballard, applied in May 2017, completed in May 2018. 1533 NW 62nd St2 duplex homes in Ballard, applied in May 2016, completed in August 2017. 1525 NW 60th St2 duplex homes in Ballard, applied in June 2016, completed in July 2017. 1720 NW 63rd St2 houses in Ballard, applied in October 2015, completed in July 2017. 1727 NW 60th St2 duplex homes in Ballard, applied in June 2016, completed in June 2017. 2237 NW 59th St2 duplex homes in Ballard, 2 stories, applied in May 2016, completed in June 2017. 1718 NW 60th St2 duplex homes in Ballard, applied in May 2016, completed in June 2017. 1736 NW 63rd St2 houses in Ballard, applied in October 2015, completed in May 2017. 355 NW 46th St2 units (1 house, 1 attached ADU) in Ballard, 2 stories, applied in November 2015, completed in April 2017. 1737 NW 63rd St2 houses in Ballard, applied in April 2015, completed in March 2017. 2031 NW 65th St2 duplex homes in Ballard, applied in November 2015, completed in March 2017. 1543 A NW 61st St2 houses in Ballard, applied in November 2015, completed in February 2017. 1717 A NW 60th St2 houses in Ballard, applied in October 2015, completed in February 2017. 1723 NW 60th St2 houses in Ballard, applied in August 2015, completed in February 2017. 1756 NW 62nd St2 houses in Ballard, applied in July 2015, completed in February 2017. 2034 NW 61st St2 duplex homes in Ballard, applied in October 2015, completed in October 2016. 1539 NW 61st St2 duplex homes in Ballard, applied in November 2015, completed in October 2016. 935 B NW 61st St1 detached ADU in Ballard, applied in April 2025, completed in November 2026. 6209 9th Ave NW1 detached ADU in Ballard, applied in October 2025, completed in October 2026. 6103 28th Ave NW1 detached ADU in Ballard, applied in May 2024, completed in October 2026. 2201 NW 64th St1 apartment in Ballard, 2 stories, applied in July 2024, completed in September 2026. 1115 NW 65th St1 detached ADU in Ballard, applied in December 2024, completed in September 2026. 652 NW 53rd St1 detached ADU in Ballard, applied in May 2025, completed in August 2026. 345 NW 52nd St1 detached ADU in Ballard, applied in November 2024, completed in July 2026. 304 NW 45th St1 detached ADU in Ballard, applied in August 2025, completed in June 2026. 3045 NW 64th St1 detached ADU in Ballard, applied in October 2022, completed in March 2026. 640 NW 53rd St1 unit in Ballard, applied in December 2025, completed in January 2026. 322 NW 51st St1 detached ADU in Ballard, applied in May 2024, completed in July 2025. 5111 6th Ave NW1 detached ADU in Ballard, applied in May 2024, completed in May 2025. 3012 NW 63rd St1 house in Ballard, 2 stories, applied in April 2021, completed in May 2025. 4775 Ballard Ave NW1 apartment in Ballard, 3 stories, applied in June 2019, completed in April 2025. 2626 NW 59th St1 unit in Ballard, applied in October 2024, completed in April 2025. 367 NW 47th St1 detached ADU in Ballard, applied in November 2023, completed in March 2025. 5808 9th Ave NW1 house in Ballard, 1 story, applied in October 2021, completed in February 2025. 6102 32nd Ave NW1 detached ADU in Ballard, applied in July 2019, completed in January 2025. 916 NW 62nd St1 detached ADU in Ballard, applied in September 2022, completed in October 2024. 349 NW 49th St1 attached ADU in Ballard, applied in July 2023, completed in August 2024. 2636 NW 57th St1 apartment in Ballard, 2 stories, applied in January 2020, completed in August 2024. 616 NW 62nd St1 detached ADU in Ballard, applied in September 2020, completed in July 2024. 926 NW 62nd St1 detached ADU in Ballard, applied in November 2022, completed in March 2024. 2815 NW 57th St1 detached ADU in Ballard, applied in February 2021, completed in November 2023. 1133 NW 62nd St1 detached ADU in Ballard, applied in September 2021, completed in September 2023. 6209 28th Ave NW1 detached ADU in Ballard, applied in April 2021, completed in March 2023. 1545 NW Market St1 apartment in Ballard, applied in October 2017, completed in February 2023. 2665 NW 63rd St1 apartment in Ballard, 2 stories, applied in April 2019, completed in December 2022. 2228 NW 61st St1 detached ADU in Ballard, applied in October 2020, completed in October 2022. 5819 6th Ave NW1 detached ADU in Ballard, applied in February 2021, completed in July 2022. 5643 3rd Ave NW1 attached ADU in Ballard, applied in November 2019, completed in June 2022. 6055 6th Ave NW1 detached ADU in Ballard, applied in July 2020, completed in May 2022. 2843 NW 60th St1 detached ADU in Ballard, applied in January 2020, completed in April 2022. 3001 NW 58th St1 house in Ballard, 2 stories, applied in December 2017, completed in March 2022. 709 NW 60th St1 attached ADU in Ballard, applied in June 2020, completed in February 2022. 844 NW 56th St1 detached ADU in Ballard, applied in July 2020, completed in November 2021. 932 NW 60th St1 detached ADU in Ballard, applied in March 2020, completed in November 2021. 835 NW 50th St1 apartment in Ballard, 1 story, applied in May 2019, completed in August 2021. 408 NW 45th St1 attached ADU in Ballard, applied in September 2019, completed in July 2021. 1141 NW 53rd St1 apartment in Ballard, 2 stories, applied in July 2019, completed in May 2021. 3006 NW 60th St1 house in Ballard, 2.5 stories, applied in September 2018, completed in March 2021. 1116 NW 62nd St1 house in Ballard, 2.5 stories, applied in November 2018, completed in March 2021. 2420 NW 60th St1 house in Ballard, 3 stories, applied in April 2018, completed in February 2021. 1526 NW 61st St1 house in Ballard, 2 stories, applied in June 2018, completed in February 2021. 1413 NW 62nd St1 detached ADU in Ballard, applied in January 2020, completed in January 2021. 5822 26th Ave NW1 apartment in Ballard, 2 stories, applied in November 2019, completed in January 2021. 5518 6th Ave NW1 attached ADU in Ballard, applied in September 2019, completed in December 2020. 3047 NW 59th St1 house in Ballard, 3 stories, applied in August 2018, completed in November 2020. 2401 NW 63rd St1 apartment in Ballard, 4 stories, applied in April 2017, completed in July 2018. 3011 NW 60th St1 house in Ballard, 2 stories, applied in November 2018, completed in October 2020. 804 NW 50th St1 house in Ballard, 3 stories, applied in October 2018, completed in October 2020. 957 NW 64th St1 detached ADU in Ballard, applied in February 2019, completed in October 2020. 3028 NW 58th St1 attached ADU in Ballard, applied in June 2019, completed in August 2020. 5813 4th Ave NW1 house in Ballard, 2 stories, applied in January 2019, completed in August 2020. 327 NW 54th St1 detached ADU in Ballard, applied in November 2016, completed in July 2020. 330 NW 50th St1 detached ADU in Ballard, applied in September 2016, completed in June 2020. 3013 NW 61st St1 house in Ballard, 2 stories, applied in January 2018, completed in May 2020. 923 NW 64th St1 detached ADU in Ballard, applied in April 2018, completed in May 2020. 934 NW 63rd St1 house in Ballard, 3 stories, applied in June 2017, completed in February 2020. 932 NW 63rd St1 house in Ballard, 3 stories, applied in January 2018, completed in February 2020. 634 NW 54th St1 attached ADU in Ballard, applied in November 2018, completed in January 2020. 1554 NW 50th St1 attached ADU in Ballard, applied in April 2018, completed in December 2019. 608 NW 62nd St1 detached ADU in Ballard, applied in May 2018, completed in December 2019. 5607 3rd Ave NW1 house in Ballard, 2 stories, applied in March 2018, completed in November 2019. 2501 NW 65th St1 apartment in Ballard, 2 stories, applied in June 2016, completed in September 2019. 932 NW 61st St1 house in Ballard, 3 stories, applied in December 2017, completed in August 2019. 2854 NW 57th St1 house in Ballard, 2 stories, applied in January 2018, completed in June 2019. 953 NW 64th St1 unit in Ballard, applied in November 2017, completed in May 2019. 938 NW 63rd St1 house in Ballard, 2 stories, applied in February 2018, completed in May 2019. 6050 7th Ave NW1 house in Ballard, 2 stories, applied in June 2017, completed in May 2019. 321 NW 48th St1 detached ADU in Ballard, applied in March 2018, completed in May 2019. 2230 NW 63rd St1 house in Ballard, 3 stories, applied in December 2017, completed in April 2019. 1415 NW 62nd St1 apartment in Ballard, 3 stories, applied in May 2017, completed in April 2019. 851 NW 56th St1 attached ADU in Ballard, applied in June 2017, completed in February 2019. 1548 B NW 62nd St1 house in Ballard, 2 stories, applied in June 2015, completed in February 2019. 2801 NW 64th St1 house in Ballard, 3 stories, applied in June 2016, completed in January 2019. 1749 NW 63rd St1 unit in Ballard, applied in July 2017, completed in December 2018. 1547 NW 63rd St1 apartment in Ballard, 1 story, applied in December 2017, completed in November 2018. 2237 NW 62nd St1 apartment in Ballard, 2 stories, applied in March 2018, completed in November 2018. 1102 NW 64th St1 attached ADU in Ballard, applied in July 2017, completed in November 2018. 2432 NW 60th St1 house in Ballard, 3 stories, applied in October 2016, completed in October 2018. 837 NW 61st St1 detached ADU in Ballard, applied in July 2017, completed in October 2018. 937 NW 59th St1 attached ADU in Ballard, applied in December 2012, completed in July 2018. 352 NW 46th St1 detached ADU in Ballard, applied in July 2017, completed in July 2018. 2014 NW 64th St1 attached ADU in Ballard, applied in August 2017, completed in July 2018. 6401 20th Ave NW1 apartment in Ballard, 2 stories, applied in October 2016, completed in June 2018. 2856 NW 60th St1 detached ADU in Ballard, applied in December 2016, completed in March 2018. 919 NW 65th St1 detached ADU in Ballard, applied in May 2017, completed in February 2018. 5822 7th Ave NW1 unit in Ballard, applied in January 2017, completed in January 2018. 2218 NW 64th St1 house in Ballard, 3 stories, applied in April 2016, completed in December 2017. 2044 NW 60th St1 attached ADU in Ballard, applied in January 2017, completed in November 2017. 3007 NW 63rd St1 detached ADU in Ballard, applied in January 2017, completed in October 2017. 3031 NW 65th St1 house in Ballard, 3 stories, applied in March 2016, completed in October 2017. 1521 NW 61st St1 house in Ballard, 2 stories, applied in November 2016, completed in September 2017. 2600 NW 63rd St1 apartment in Ballard, 1 story, applied in December 2016, completed in September 2017. 926 NW 63rd St1 house in Ballard, 2 stories, applied in October 2016, completed in August 2017. 2859 NW 59th St1 house in Ballard, 2 stories, applied in February 2016, completed in July 2017. 812 NW 63rd St1 house in Ballard, 3 stories, applied in March 2016, completed in June 2017. 2226 NW 62nd St1 apartment in Ballard, 3 stories, applied in March 2016, completed in June 2017. 5012 8th Ave NW1 detached ADU in Ballard, applied in February 2016, completed in April 2017. 364 NW 48th St1 detached ADU in Ballard, applied in January 2016, completed in March 2017. 2827 NW 65th St1 house in Ballard, 3 stories, applied in December 2015, completed in February 2017. 2407 NW 59th St1 apartment in Ballard, 3 stories, applied in May 2016, completed in January 2017. 6042 7th Ave NW1 attached ADU in Ballard, applied in June 2016, completed in December 2016. 1736 NW 62nd St1 house in Ballard, 3 stories, applied in August 2015, completed in September 2016. 2837 NW 60th St1 attached ADU in Ballard, applied in February 2016, completed in April 2016.